New Melton Campus progressing well...

Sunday 10th February, 2019

The building work at the new state-of-the art campus at Melton is making good progress.

Current position of the project in early February..

  • Achieved lock up on main building, with Sports hall locked up by EOM
  • Wall linings have started on timber stud and external walls, ceiling grid will start in the primary building next week which allows us to get started on the partition walls.
  • Services (Electrical, Mechanical, Hydraulics) rough in is well underway and hope to be completed by EOM
  • Fixed joinery design and final internal finishes selections are being finalised by architect
  • Site facilities are midst relocation to the nature reserve (council approved this)
  • Earthworks levels have been pegged out and major earthworks for carparks and play areas etc are starting next week.

 

 

New Melton Campus progressing well...

 

Campus Locations Community Support Suggestion Box Acedemic Results

23 SCANLON DRIVE EPPING 3076

P.O. Box 224 Campbellfield VIC 3061

Ph (03) 8199 8277

 

Contact us|Site map|Terms of use|Disclaimer|Privacy policy|Miscellaneous|Sitemap   |   Design by Dynamic Multi Media   |   Administrator Login